NEW HHS: Renderings, construction timetable

The gym complex would contain a game gym seating 900 and a practice gym.

View the Slideshow

 

HHS project at a glance


• Cost: $53 million (total)
• Architectural work and project management: $2.7 million (ClarkNexsen)
• Square footage: 161,500
• Construction time: 2½ years
• Includes: Classroom building with band room, vocational classrooms and cafeteria; new gym seating 1,000, practice gym, field house adjoining the north end of Dietz Field, auditorium seating 900, courtyard and dropoff loop between the Stillwell building and new campus.
• Landscape design: Limited to zoning code compliance.
• Not budgeted: additional land for parking, HHS track improvements.

Construction timeline


• In coming weeks the county will hire a construction manager at risk. The contractor will guarantee the price and take on the financial risk of coming in over budget.
• Complete design: Summer 2017.
• Complete construction documents: February 2018.
• Bid subcontracts: April 2018.
• Start construction: May 2018 (projected 610 days)
• Completion construction: May 2020.
• Install furniture and fixtures: May-August 2020.
• Students arrive: August 2020.
• Phase 2 site work and demolition: June-October 2020.